Keller Avenue Project Updates

Construction Updates

Keller Avenue Construction Project Update for September 21, 2021:  

 

The concrete guys are here pouring curb and gutter and will finish today.

 

B & B Electric is here running electric for the street lights and electric and fiber for the stop lights.

 

Crews will be back later next week to work on sidewalks.